Production basis
Mould volume, batches, operating hours, density, product mix and saleable output.
AAC investor guide · Supplier due diligence
An AAC plant proposal is more than a machinery list. Compare the production basis, complete scope, operating evidence and accountability behind every offer.
Designed for investors, technical teams and corporate purchase teams.
The direct answer
Compare AAC plant suppliers using the same production assumptions, equipment boundaries, automation definition, utility basis, manpower model, commissioning responsibility and acceptance conditions.
A quotation becomes comparable only after its inclusions, exclusions and evidence are visible.
A complete comparison
Each factor connects a technical choice to commercial risk, operational stability or future flexibility.
Mould volume, batches, operating hours, density, product mix and saleable output.
Machinery, auxiliaries, controls, handling systems and battery limits.
Where manual intervention remains in normal operation and fault recovery.
Power, steam and water assumptions on the same production basis.
Operators, helpers, maintenance and supervision required per shift.
Blocks, panels, sizes, density range and quality-control requirements.
What the supplier designs, manufactures, assembles and tests.
Comparable references supported by operating records—not observation alone.
Ownership of integration, commissioning, training and stabilization.
Test conditions, measurements, exclusions and acceptance criteria.
Warranty, response process, documentation and parts availability.
Future capacity, panel integration and layout constraints.
Evaluate
A supplier presentation can establish interest. It cannot replace measurable assumptions, physical verification or contractual clarity.
Place each offer into one scope-responsibility matrix. Record supply, erection, cabling, piping, integration, commissioning and testing for every plant section.
Request mould volume, batches per hour, operating hours, pre-curing constraints, cutting cycle, autoclave loading, curing cycle and saleable-output assumptions.
Identify where operators initiate movement, confirm sequences, recover faults, record quality data or manually handle material. Compare functions—not labels.
Separate connected load from consumption. Compare power, steam, water and manpower for the same production, product mix and shift pattern.
Comparison rule
If two capacity or utility figures use different assumptions, they are not yet comparable.
Physical verification
01 / Workshop
A workshop visit should be an evidence review—not a visual judgement of size or housekeeping alone.
Do not infer financial strength from workshop appearance. That requires separate due diligence.
02 / Running plant
Select references close to the proposed capacity, raw-material route, automation level, age and product mix.
Observe the plant, speak with the owner and operating team, then cross-check recollections with records.
Decide
The objective is not to find the longest proposal. It is to find the configuration that fits your project and can be verified.
Unsupported capacity, incomplete safety responsibility, unclear acceptance terms or an essential missing plant section should be treated as decision gates—not merely low-scoring items.
Before you finalize
Investor questions
No. Price should be compared only after scope, assumptions, performance obligations and lifecycle responsibilities are normalized. A lower price may be commercially sound when the proposal remains technically complete and verifiable.
One closely comparable reference provides useful evidence. Additional references improve confidence when technology, capacity, raw materials, product mix or plant age differ.
Map the complete process and record every routine action, manual transfer, operator confirmation, fault-recovery task and quality-data entry. Compare functions rather than labels.
Ask which assumptions convert mould volume and production cycles into saleable cubic metres per day. Without those assumptions, headline capacities are not directly comparable.
Clear accountability is more important than a particular contracting model. Every interface needs a competent, named and contractually responsible party.
A plant reasonably close to the proposed technology, capacity, raw-material route, product mix and automation level—and where operating records can be reviewed.
Before the purchase order
Share your proposed capacity, product mix and supplier scope sheets. Identify technical deviations, incomplete responsibilities and questions that should be resolved before finalization.